Additional Information:
Type of plant: Fertilizer
Task: Remove existing internals, check of converter shell, install new internals
Materials used: Stainless Steel 1.4571
Techniques/Licensor: Casale
Duration: 21 days – 24/7 basis
Special Challenges: Partial work under nitrogen